Kisoro attacks Geses Uganda limited

Kisoro district authorities have castigated Geses Uganda limited, a company constructing Mwumba progressive seed secondary school for its slow pace in executing its duties.

Ad

According to the Kisoro district engineering department, construction progress stands at less than 45 percent after nine months of work out of two years of contract.

This was confirmed yesterday during site monitoring, assessment and supervision of work progress by Kisoro district officials led by Chief Administrative officer Manjara Badru Mayanja.

Sources at the site revealed that work progress is being frustrated by local labourers that do not report to work consistently. It is said that these casual labourers disappear for a long time after receiving payments and return when they run short of money.

The Kisoro Resident district commissioner, Hajji Shafiq Sekandi advised Geses administrators to employ more workers if work must be done in accordance with the agreed schedule.

He commended the construction company for the quality work being done and said that the company should bring in its workers if the progress speed is being limited by unreliable local labourers.

He pledged to speak to UNRA leadership over the poor state of the road that has been another stumbling block. Sekandi noted that Geses workers should utilise this dry season to move more materials to the site in order to have a smooth run of work that will in-turn lead to faster completion of the contract.

On behalf of the district Engineer, Bazubaze John noted that workers are very few and some structures like toilets have not been started on while others are being abandoned yet the contract plan indicates that all structures at the site should move at the same pace. He added that the work progress is behind schedule.

The Kisoro district Education officer, Mwunvaneza Emmanuel said that he is not impressed with the speed and appealed for double efforts.

Meanwhile the Geses Company limited site manager at Mwumba progressive ss, Sejemba Godfrey acknowledged the officials concerns and promised to hire more workers.

According to Didan the site supervisor on behalf of the district, Geses has reduced its workers at Mwumba from 68 in April to now 16 including both professionals and casual labourers.

CAO’s office also revealed that over 200 million shillings was returned to the central government’s collection bank account at the end of last financial year because the district would not pay it to Geses company limited due to little work on ground.

The contract sum is 3.3 billion shillings and only over 1 billion has been paid to Geses by Kisoro district local government

 