National Water and Sewerage Corporation(NWSC) is expanding the Kapeeka Water Supply System to serve over 100 villages in three districts of the central part of Uganda. The districts are; Mityana, Nakaseke and Kiboga
Speaking during the Inspection of the projects works at Kapeeka in Nakaseke district, NWSC MD Dr. Eng Silver Mugisha warned the contractor against cost over runs. He asked them to deliver the project on time and work with the communities who are the initial beneficiaries.
Dr. Silver said the project will be completed by April 2021 and will increase water supply from 2.5 million to 7million litres of water per day, boost industrialization at Kapeeka business park, improve sanitation and health in the said districts.
He advised residents to jealously protect River Mayanja which is central to the heart of the project.
The project scope includes:
•Bulk water transfer to Semuto Sub county
•Bulk water transfer to Bukomero town
•Bulk water transfer to Kapeeka Industrial park
•Imrove current water production from 2.5million litres/day to 7million litres/day
•Upgrade of electro-mechanical equipment.
•Upgrading of raw water intake
•Construction of two additional water treatment lines including; an aerator, flocculator, calculator, clarifier, filter and ancillary works.
•Construction of a new pump house
•Construction of a 150m3 steel backwash water tank
•Laying of a parallel steel treated water pumping main
•Construction of a new 600m3 steel reservoir
installation of raw water and treated water pumps
•Construction of staff houses
The project when completed will serve Singo Army barracks, 60 villages in Kapeeka town, Kapeeka Industrial park, 20 villages in Kikandwa-Mityana district , Masiliba, Kakyenga, Nakatoke, Kituma, 30 villages in Bukomero-Kiboga district among other areas.
Richard Ogwal the manager NWSC Kapeeka area also said that they target to have completed the project by February 2020.
Kapeeka water works is funded using internally generated NWSC resources with support from the Government of Uganda.
Meanwhile Kampala City water production will also be boosted when the Ggaba water works are completed. NWSC is undertaking construction of a giant water plant that will serve the growing demand.
“We are working on massive infrastructure to add over 160 million litres of water per day to Kampala. The combined production from Ggaba (240 million litres /day) and Katosi (240 million litres design capacity and 160 production for phase 1) will produce a today of 400 million litres of water per day and bridge the water supply gaps in the city by February 2020.” Said Dr. Mugisha.
He said the Katosi project will solve water supply challenges in Kungu, Najjera, Kulambiro, parts of Ntinda, Ssonde, Gayaza, Kanyanya, Kyaliwajjala, Kira, Kitikifumba, Matugga, Kawanda, Mukono, Wakiso and other areas experiencing water supply challenges in the Kampala Metropolitan service area.
He added that NWSC in partnership with the Danish business is working on a new water works at Kaazi along Entebbe road. The water works when completed will boost water supply along Entebbe road, Mpigi, Wakiso and the surrounding areas
The Corporation Manager in charge of Infrastructure projects supervision, Eng. Herbert Mujuni, said Katosi water supply project is 75% complete with all civil works done.
“The contractor is installing electoral mechanical equipment and system tests and the facility will start in December to March 2021” he assured city dwellers.